Suzuki
(Bandit 1200)
Project
Created - January 2008 - May 2008
Ladies and Gentlemen, this is - "Flash Bandit"
Our first project build for 2008
Rebuild and Restoration
to be carried out by Ade
Comments or questions
Email
![]()
In fair condition. Engine
is excellent - 11.000
Miles on the clock and pulls like a train.
This is going to be one of Ade's special custom jobs..
Total project time - 4 months to
complete. Approx 400 hours.
How the bike stands when
purchased 12th January 2008


![]()
22nd January 2008:
The strip down has started. The arse end removed and all the bits off for
Chroming, Alloy Polishing
and paint. Rear shock removed ready for for the jack up kit.



![]()
20th February 2008:
Engine now stripped, painted & polished.


Seat Re-shaped and re-covered.

New wave discs have arrived.

![]()
15th March 2008:
Rear end now painted, polished & Chromed, including every Nut, Bolt & Washer
re-chromed!
New braided brake lines, pads, waive discs etc, now fitted to the bike.



We raised the rear end by 2
inches, this made things a little tight for space..
Ade always has the solution!



![]()
1st April 2008:
Front end stripped down.
All parts in for paint, polish & Chrome.


![]()
2nd April 2008:
As usual on this project, everything Chromed and polished.
Fork legs, stantions, Yokes, Front wheel, every nut, bolt and washer!
New Goodridge braided hoses, fork brace & brakes.






![]()
13th April 2008:
Into the final stages - all last metal polishing and detail.
Awaiting the custom paint bodywork for completion.


![]()
10th May 2008:
A change of mind with the rear end. We decided the rear end was that nice it had
to be shown more.
So, we cut down the end can into a stubby! The extra 3 inches up on the rear
certainly shows now.

Now this is gonna sound fruity!!

![]()
The finished bike. Now the
paint is done, final polishing of the engine casings and details complete.




![]()
![]()
Before